In progress
- Contract value
- $68,400
- Next step due
- November 25, 2026 (in 2 days)
- Owner
- Project Manager
- In this stage
- since 9 days ago
- Trade
- Decking and outdoor living
- Office
- Pittsburgh
- Crew
- Deck crew 4
- Scope
- 24 by 16 foot composite deck, gable roof over the back half, one curved step, and a fan in the roof
- Materials
- TimberTech composite decking, black aluminum rail, and a roof shingled to match the house
- Paying by
- 30% deposit, 40% at the framing inspection, 30% at completion
- Permit and inspections
- Township building permit. Footings passed; framing inspection booked
- Job address
- Hollow Oak Drive, Upper St. Clair (illustrative)
- Invoiced
- $20,520 (paid)
- Job cost
- $40,900
- Gross margin
- $27,500 (40%)
Tasks
- Meet the inspector for the Brennan framing inspection, then send the progress invoiceProject Managerin 2 days
History
- Project Manager wroteyesterdayFraming done. Inspection booked for Tuesday, then the progress invoice goes out.
- Project Manager moved it to In progress9 days agoFootings dug and poured. Footing inspection passed.
- Scheduler moved it to On the scheduleOct 24Permit issued. On Deck crew 4's calendar for two weeks from now.
- Production Administrator moved it to Material orderedSep 29TimberTech package and rail ordered. Permit drawings submitted.
- Sales Estimator moved it to Signed, deposit inSep 26Signed. Deposit paid by card.
- Sales Estimator moved it to Estimate sentSep 21Estimate sent five days after the visit, with Ryan's drawing of the roof.
- Scheduler moved it to Estimate scheduledSep 7First open estimate slot is nine days out.
- Call Center opened it in New leadSep 6Website form with photos of the old deck. Wants a covered deck they can use when it rains.