Punch list
- Contract value
- $38,700
- Next step due
- November 24, 2026 (tomorrow)
- Owner
- Project Manager
- In this stage
- since 3 days ago
- Trade
- Siding
- Office
- Pittsburgh
- Crew
- Siding crew 1
- Scope
- Replace the vinyl siding with fiber cement lap and board and batten on the gables
- Materials
- James Hardie lap and board and batten, Evening Blue, with Arctic White trim
- Paying by
- 30% deposit, balance at completion
- Permit and inspections
- None needed. Confirm
- Job address
- Pine Creek Road area, Wexford (illustrative)
- Invoiced
- $11,610 (paid)
- Job cost
- $23,600
- Gross margin
- $15,100 (39%)
Tasks
- Fix the Fitzgerald punch list and do the final walkProject Managertomorrow
History
- Project Manager moved it to Punch list3 days agoFinal walk with Katie: J-channel at the back door, one dented corner piece, and the garage downspout. Fixing them before the final invoice.
- Project Manager moved it to In progress14 days agoSiding crew 1 started.
- Scheduler moved it to On the scheduleOct 29
- Production Administrator moved it to Material orderedOct 10
- Sales Estimator moved it to Signed, deposit inOct 9Signed the day the estimate arrived.
- Sales Estimator moved it to Estimate sentOct 8
- Scheduler moved it to Estimate scheduledOct 6
- Call Center opened it in New leadOct 6