In progress
- Contract value
- $19,900
- Next step due
- November 23, 2026 (today)
- Owner
- Project Manager
- In this stage
- since yesterday
- Trade
- Roofing
- Office
- Butler
- Crew
- Roofing crew 2
- Scope
- Tear off and replace 24 squares. Change order pending for rotted plywood over the back porch
- Materials
- GAF Timberline HDZ shingles, Hickory
- Paying by
- 30% deposit, balance at completion
- Permit and inspections
- Roofing permit issued
- Job address
- Freedom Road area, Cranberry Township (illustrative)
- Invoiced
- $5,970 (paid)
- Job cost
- $13,600
- Gross margin
- $6,300 (32%)
Tasks
- Call the Pratts about the rotted decking and get the change order signedProject Managertoday
- Approve the Pratt change order price before it goes outMatt Haldentoday
History
- Project Manager wrote2 hr agoFound 14 sheets of rotted plywood over the back porch. Tarped. Crew moved to the front slope while the change order is approved.
- Project Manager moved it to In progressyesterdayTear-off started.
- Scheduler moved it to On the schedule8 days ago
- Production Administrator moved it to Material orderedNov 5
- Sales Estimator moved it to Signed, deposit inNov 3
- Sales Estimator moved it to Estimate sentOct 31
- Scheduler moved it to Estimate scheduledOct 21
- Call Center opened it in New leadOct 20Called from a Google ad.