Ordering and scheduling

Ordering

  1. Deposit in, then order. The production administrator builds the order from the signed estimate: squares and bundles, siding and trim pieces, decking and rail, fasteners, and flashing.
  2. Check lead times before promising a date. As a rule of thumb (confirm each):
  3. GAF shingles: usually in stock.
  4. James Hardie with factory color: one to three weeks, longer for a backordered color.
  5. TimberTech and rail: in stock to three weeks, by color.
  6. DaVinci: several weeks.
  7. Decks in general: about two weeks for material, per the website.
  8. Send the order to the supplier rep and log the confirmed delivery date on the job.
  9. Book the dumpster 48 hours before tear-off.

Scheduling

  • A job goes On the schedule only when the material is confirmed and the permit is issued.
  • Friday at 11:00 AM: next week's calendar for every crew, checked against the forecast.
  • Every homeowner gets a text before the crew comes: the day, the arrival time, what to move, and who their project manager is.
  • Rain moves a roof start. The homeowner hears about it the same hour the decision is made, not the morning of.
  • Deck builds run about one to two weeks once material arrives, per the website.

Confirm: who owns the crew calendar today, and whether it lives in ServiceTitan or somewhere else.