Ordering and scheduling
Ordering
- Deposit in, then order. The production administrator builds the order from the signed estimate: squares and bundles, siding and trim pieces, decking and rail, fasteners, and flashing.
- Check lead times before promising a date. As a rule of thumb (confirm each):
- GAF shingles: usually in stock.
- James Hardie with factory color: one to three weeks, longer for a backordered color.
- TimberTech and rail: in stock to three weeks, by color.
- DaVinci: several weeks.
- Decks in general: about two weeks for material, per the website.
- Send the order to the supplier rep and log the confirmed delivery date on the job.
- Book the dumpster 48 hours before tear-off.
Scheduling
- A job goes On the schedule only when the material is confirmed and the permit is issued.
- Friday at 11:00 AM: next week's calendar for every crew, checked against the forecast.
- Every homeowner gets a text before the crew comes: the day, the arrival time, what to move, and who their project manager is.
- Rain moves a roof start. The homeowner hears about it the same hour the decision is made, not the morning of.
- Deck builds run about one to two weeks once material arrives, per the website.
Confirm: who owns the crew calendar today, and whether it lives in ServiceTitan or somewhere else.