Permits and inspections
The company works in more than 300 municipalities, and each one runs permits its own way. That is exactly the kind of knowledge that lives in one person's head until it's written here.
Decks and outdoor spaces
- Ryan or the design team draws the permit set from the signed design.
- The production administrator submits it to the township with the application and fee.
- Inspections, in order: footings before the concrete, framing before the decking goes on, and the final.
- Electrical and gas permits for outdoor kitchens and fireplaces are pulled by those subs.
- The progress invoice goes out after the framing inspection passes.
Roofing and siding
- Some townships want a permit for a full roof replacement; some don't. Confirm the list of where the company always pulls one.
- Siding replacement and repairs usually need none. Confirm.
Township notes
A few for the AIOS to start from. Each one gets a line as the office learns it.
| Township | What to know |
|---|---|
| Upper St. Clair | Confirm: lead time for a deck permit and how to book inspections |
| Hampton Township | Confirm |
| Cranberry Township | Confirm |
| North Strabane | Confirm |
Rules
- No crew starts a deck without the permit in hand.
- A failed inspection is a punch list item on the job, with a date to re-inspect.